FOGBANK is a code name given to a material used in nuclear weapons such as the W76, W78 and W80.[1]

FOGBANK's precise nature is classified; in the words of former Oak Ridge general manager Dennis Ruddy, "The material is classified. Its composition is classified. Its use in the weapon is classified, and the process itself is classified." Department of Energy Nuclear Explosive Safety documents simply describe it as a material "used in nuclear weapons and nuclear explosives" along with Lithium hydride (LiH) and Lithium deuteride (LiD), Beryllium (Be), Uranium hydride (UH3), and Plutonium hydride. Many arms experts believe that FOGBANK is an aerogel material which acts as an interstage material in a nuclear warhead, i.e. a material designed to become a superheated plasma following the detonation of the weapon's fission stage, the plasma then triggering the fusion-stage detonation.

History

It has been revealed by unclassified official sources that FOGBANK was originally manufactured in Facility 9404-11 of the Y-12 complex in Oak Ridge, Tennessee from 1975 until 1989, when the final batch of W76 warheads were completed. After that the facility was mothballed, and finally slated for decommissioning by 1993. Only a small pilot plant was left, which had been used to produce small batches of FOGBANK for testing purposes.

In 1996, the US government decided that large numbers of its nuclear weapons would require to be replaced, refurbished, or decommissioned. Accordingly, the Department of Energy set up a refurbishment program aimed at extending the service lives of older nuclear weapons. In 2000, the National Nuclear Security Administration (NNSA) specified a life-extension program for W76 warheads that would enable them to remain in service until at least 2040.

It was soon realized that the FOGBANK material was a potential source of problems for the program, as few records of its manufacturing process had been retained when it was originally manufactured in the 1980s, and nearly all staff members who had expertise in its production had either retired or left the agency. The NNSA briefly investigated sourcing a substitute for FOGBANK, but eventually decided that since FOGBANK had been produced previously, they would be able to repeat it.

With Facility 9404-11 long since decommissioned, a brand new production facility was required. Delays arose during its construction, and in addition, engineers repeatedly encountered failure in their efforts to produce FOGBANK. As one deadline after the other expired, and the schedule was pushed back again and again, the NNSA eventually decided to invest $23 million to attempt to find an alternative to FOGBANK.

In March 2007, engineers finally devised a manufacturing process for FOGBANK. Unfortunately, the material turned out to have problems when tested, and in September 2007 the FOGBANK project was upgraded to "Code Blue" status by the NNSA, making it a major priority. In 2008, following the expenditure of a further $69 million, the NNSA finally managed to manufacture FOGBANK, and 7 months later, the first refurbished warhead was handed over to the US Navy, nearly a decade after the commencement of the refurbishment program. However, in May 2009 a US Navy spokesman said that they had not received any refurbished weapons to date. The Energy Department stated that the current plan was to begin shipping refurbished weapons in the fall of 2009, two years behind schedule.[2]